LVL North, the Largest Modular Apartment on the East Coast

410 Multi-Family Units Cut Down 22 Months of Construction

Spanning an entire city block, 510 N. Broad is VBC’s largest Multi-Family development and the largest modular apartment on the East Coast. It offers a variety of modern features with a sleek design, an in-building retail grocery store, and a roof-top community space. Working with Alterra Property Group, VBC designed this complex to house a large range of studio, junior one-bedroom, traditional one-bedroom, two-bedroom units, and ample amenity spaces. By using modular construction and VBC’s ability to turn out modular units quickly, the 510 N. Broad project saved 22 months of construction time compared to traditional construction.

This build is in the heart of downtown Philadelphia on one of the busiest traffic corridors in the city. Modules were delivered to the off-site storage lot several months before installation began. Due to the considerable size of the project, more than one off-site storage location was chosen. The set took approximately 55 days, with a module being set roughly every 45 minutes.

Timeline

Total months
18 Months
Total Construction Time
days
55 Days
Module Set Time
finished
22 Months
Estimated Time Saved vs. Traditional Construction

Building Specs:

  • Number of Units: 410
  • Area: 23,840 M2
  • Asset Class:

    Multi-Family Apartment

  • Total Project Levels: 7
  • Total Modular Levels: 5

Project Team:

  • Owner: Alterra Property Group
  • Developer: Alterra Property Group
  • Architect of Record: VBC
  • Modular Installer: VBC
  • General Contractor: Clemens Construction
DJI_0282

Photo Gallery

Image 1
Studio Layout with VBC Furniture and Fit Out
slider 4
Lounge Area
ice-122330608-71171510_3XL-970698
Typical Bedroom
slider 3
Kitchen Area
slider 10
En Suite Bathroom
slider 2
Lounge
Image 2
Living Area
Image 4
VBC-Supplied Kitchen
510-Broad-768x476
VBC_510NBroad_ProgressDrone7-19-22-02
Aerial View of Finished Building
VBC_510NBroad_SetPhase4Drone-03
Aerial View During Construction
Image 3
Completed Exterior

Client Testimonial

Project Location

Screen Shot 2023-08-17 at 5.44 1

For us, it’s about speed and consistency.

When we do modular, we save between 6-12 months of construction time.

Jared Kern

Alterra Property Group

View more projects...

BREEAM Certified citizenM Flagship Hotel

370 Unit Hospitality Build

Tower of London, United Kingdom

Speedily Solving the Student Housing Crisis

324 Unit Student Housing Facility

1600 N. 11th St. Philadelphia, PA

Over 4,000 Rooms Fitted Out for citizenM

19 Hotels and Counting

Modern Features with a Built-In Grocery Store

410 Multi-Family Market-Rate Apartments

510 N. Broad St. Philadelphia, PA

A Future Forward Premium Steel Build

250 Unit Hospitality Build

Airport Way Luton LU2 9LFF, United Kingdom